Impact Manufacturing's adjustable joist brackets connect steel I-beam wall braces to your floor joists so a bowing or leaning basement wall can be held in place. This page covers how to pick the right bracket, which beams and hardware it works with, how to install it, and how to torque it safely.

Before you start: Have a licensed structural engineer review your wall. They should confirm bracket spacing, which bracket type to use, and, for parallel joists, which kind of joist strut to use.

Choosing the Correct Bracket

Which bracket do I need?

It depends on which way your floor joists run compared to the wall you're repairing:

Your joists run… Use this bracket Attaches to
Perpendicular to the wall (they meet the wall end-on) Double Joist Perpendicular Bracket (centered) The bottom of 2 joists
Perpendicular to the wall Single Joist Perpendicular Bracket (offset) The side of 1 joist
Parallel to the wall (they run alongside it) Parallel Joist Bracket A joist strut (2×8 lumber or 8" steel flat plate)
  • Side-view diagram of floor joists perpendicular to a foundation wall

    Perpendicular Joists

    Perpendicular floor joist

    Side View

  • Top-view diagram of floor joists perpendicular to a foundation wall

    Perpendicular Joists

    Perpendicular floor joist

    Top View

  • Side-view diagram of floor joists parallel to a foundation wall

    Parallel Joists

    Parallel floor joist

    Side View

  • Top-view diagram of floor joists parallel to a foundation wall

    Parallel Joists

    Parallel floor joist

    Top View

  Wall Bracing Brackets FAQ

What makes the Impact bracket different from other wall bracing brackets?

The most common reason I-beam wall repairs fail is the top bracket rolling and pulling its fasteners out of the floor joists. Impact's Slip Bushing System prevents this. It sends the load to the base of the fasteners and pushes lateral force back toward the joists, so the bracket stays put.

The bracket also has the largest, strongest adjustable Torque Stud on the market. The slip bushing makes the nut easier to torque and adjust during installation and yearly maintenance.

Can the bracket straighten my wall?

Not right away, and it isn't guaranteed. The bracket's main job is to hold the wall where it is now. With careful yearly maintenance (see "Torquing the Bracket" below), some walls can move closer to plumb over time. Others will need more repair work to get there. Never over-torque the bracket to force a wall back into place.

How far apart should the brackets be?

Your structural engineer should set the exact spacing. As a general limit, Impact recommends:

  • Double Joist bracket: no more than 4 joists between brackets
  • Single Joist bracket: no more than 2 joists between brackets

What size I-beams do the brackets fit?

The Channel Bracket comes in two sizes, one for S4 I-beams and one for W4 I-beams. The Lower Floor Bracket fits S4×7.7, S4×9.5, and W4×13 beams, plus C-channel bracing.

Sizing and Hardware

What size is the all-thread on the adjuster?

It's 1-1/4" solid steel.

How much adjustment does the bracket have?

About 4 inches.

My joists aren't exactly 16" on center. Will the bracket still line up?

Most likely, yes. Both the adjustable and stationary perpendicular brackets have slotted (oval) holes, so the fasteners can land in the center of the joist even when the spacing is a little off. This is common in older homes. The Double Joist plate fits joist spacing from 14-7/8" to 17-1/8" on center.

What fasteners does each bracket use?

Bracket Fasteners
Double Joist (Perpendicular) Six 3/8" × 3-1/2" lag screws
Single Joist (Perpendicular) Four 3/8" × 2-1/4" Grade 8 hex bolts, with washers and lock nuts
Parallel – wood strut Four 3/8" × 2-1/4" Grade 8 hex bolts, with washers and lock nuts
Parallel – steel strut Four 3/8" × 1" Grade 8 bolts
Lower Floor Bracket Galvanized 5/8" wedge anchors, 4" to 4-1/2" long
Crowfoot wrench adapter diagram showing 46 mm opening and half-inch drive

 What tool do I need to torque the bracket? 

The 46mm Crow's Foot Wrench Adapter. It fits a 1/2" drive torque wrench and goes onto the bracket's 1-1/4" Torque Nut, so you can read the exact torque as you tighten.

Go to Product
Lower floor bracket diagram showing dimensions and mounting holes

What is the Lower Floor Bracket for?

It anchors the bottom of the I-beam or C-channel to the basement floor. It fits S4×7.7, S4×9.5, and W4×13 I-beams.

Go to Product

Wall Bracing Bracket Installation

Tips for every bracket

  • Keep the Torque Nut as close to the Channel Bracket as possible. Only extend the Torque Stud if something is in the way.
  • Mount the Joist Plate as close to the I-beam as possible. This leaves the most room to extend the Torque Stud later.
  • Pre-drill every hole with a 5/16" drill bit.
  • Don't over-tighten the lag screws or bolts.

How do I install the Double Joist (Perpendicular) bracket?

  1. Hold the Joist Plate against the bottom of two joists, snug against the installed I-beam.
  2. Pre-drill the two center holes in each joist, deep enough for the 3-1/2" lag screws.
  3. Drive the lag screws with an impact wrench, without over-tightening.
  4. Pre-drill the remaining four holes and drive the last four lag screws.
  5. Turn the Torque Nut by hand until the Channel Bracket is snug against the I-beam.
  6. Use the torque wrench and crow's foot adapter to tighten to spec (see the torque table below).

How do I install the Single Joist (Perpendicular) bracket?

  1. Hold the Joist Plate against the side of one joist, snug against the installed I-beam.
  2. Pre-drill the two top holes all the way through the joist.
  3. Put in two 3/8" Grade 8 hex bolts. On the back side of each one, add a 3/8" washer and a 3/8" lock nut.
  4. Pre-drill the remaining two holes and put in the last two bolts the same way.
  5. Turn the Torque Nut by hand until the Channel Bracket is snug against the I-beam.
  6. Use the torque wrench and crow's foot adapter to tighten to spec.

How do I install the Parallel Joist bracket?

When your joists run parallel to the wall, install a joist strut first. This is a crosspiece made of 2×8 lumber or 8" steel flat plate. Your engineer should choose which one to use.

  1. Hold the Joist Plate against the bottom of the joist strut, snug against the installed I-beam.
  2. Pre-drill two holes all the way through the strut.
  3. Put in two 3/8" Grade 8 hex bolts. On the back side of each one, add a 3/8" washer and a 3/8" lock nut. Use 2-1/4" bolts for wood struts and 1" bolts for steel struts.
  4. Pre-drill the remaining two holes and put in the last two bolts.
  5. Turn the Torque Nut by hand until the Channel Bracket is snug against the I-beam.
  6. Use the torque wrench and crow's foot adapter to tighten to spec.

Torquing the Bracket

What torque should I use?

Wall type Torque
Cinder block / CMU 40 ft-lbs
Poured concrete (monolithic) 60 ft-lbs

How often should I re-torque?

Once or twice a year at most. The best time is the driest part of the year. During dry weather, foundation walls often shift slightly outward, which can leave a small gap between the beam and the wall. Tightening to spec closes that gap and holds the wall in its new position. Done this way year after year, some walls can move closer to plumb.

What happens if I over-torque?

Over-torquing can crack the joists or pull out the fasteners. This includes:

  • Going past the torque specs above
  • Cranking the nut harder to try to straighten the wall faster
  • Re-torquing more than twice a year

Installed Impact Bracket System